淮河临淮岗洪水控制工程洪水调度数学模型应用 |
吴时强,吴修锋,周辉,周杰,范子武
|
南京水利科学研究院,江苏,南京,210029;水文水资源与水利工程国家重点实验室,江苏,南京,210029
|
|
摘要: |
利用所建立的临淮岗工程洪水调度运行模型,针对临淮岗工程三湖圈圩方案,就百年一遇洪水情况下临淮岗工程洪水调度运行方案进行了研究.按照工程上下游控制条件,分析研究临淮岗工程以及行蓄洪区运用方式,得出通过适当的工程调度可以达到百年一遇洪水控制设计标准,为临淮岗工程运行调度方案的确定提供可靠科学依据. |
关键词: 淮河 临淮岗工程 洪水调度 数学模型 剖开算子法 |
DOI: |
分类号:TV122 O242.1 |
基金项目:国家"十一五"科技支撑项目"防洪工程体系洪水调控模拟关键技术" |
|
Application of a flood control operation numerical model for Linhuaigang Project on Huai River |
WU Shi-qiang,WU Xiu-feng,ZHOU Hui,ZHOU Jie,FAN Zi-wu
|
WU Shi-qiang1,2,WU Xiu-feng1,ZHOU Hui1,ZHOU Jie1,FAN Zi-wu1,2(1.Nanjing Hydraulic Research Institute,Nanjing 210029,China,2.State Key Laboratory of Hydrology-Water Resources and Hydraulic Engineering
|
Abstract: |
By use of the flood control operation model for Linhuaigang flood control project on Huai River,the flood control operation program for three-lake-link plan under 1% frequency flood is studied.According to the control conditions of up-and down-stream boundaries,the operation schemes for Linhuaigang project and flood retention are analyzed,and can meet the requirement of flood control criterion.It is demonstrated that the model is useful to forecast the flood process and determine optimal operation modes for... |
Key words: Huai River Linhuaigang Project flood control operation numerical model operator-splitting FEM |