外高桥顺岸桩基码头泥沙回淤及分析 |
张金善1,刘卫平2,戴贤凯3
|
1. 南京水利科学研究院,江苏,南京,210029;南京师范大学,地理科学学院,江苏,南京,210093 2. 上海国际港务(集团)有限公司,上海,200012 3. 南京水利科学研究院,江苏,南京,210029
|
|
摘要: |
顺岸式桩基码头前沿会发生较为严重的泥沙淤积.以长江口外高桥港区码头为例,根据现场实测水深资料,并结合物理模型试验及数学模型计算的结果,分析建码头后影响码头前沿泥沙回淤的因素.桩基的阻水作用,减小了码头前沿的水流速度,是码头回淤的主要原因。 |
关键词: 桩基码头 泥沙回淤 外高桥港区 水作用 物理模型试验 水深 泥沙淤积 现场实测 水流速度 资料 |
DOI: |
分类号:TV148 U656 |
基金项目: |
|
Analyses on sediment deposition along pile wharf of Waigaoqiao Port |
ZHANG Jin-shan
|
ZHANG Jin-shan~
|
Abstract: |
There is a serious sediment deposition in the wharf apron of an alongshore pile wharf. Based on the in-situ measured data of water depth and results of physical model tests and mathematic model calculation, the influencing factors on the sediment deposition in the wharf apron after construction of wharfs are analyzed taking the wharfs in Waigaoqiao Port in the Yangtze River estuary as an example. Analysis results show that the main factor of sediment deposition is the decrease of flow velocity in the wharf apron caused by pile resistance effects. |
Key words: sediment deposition,variation of water depth,resistance effect,velocity,beach slope,alongshore pile wharf, |