摘要: |
分析了蘑菇湖水库泄水涵洞下游消能的现状及存在的问题,通过对垂直边墙水平扩散消力池的水力计算和水工模型试验,提出了在消力池尾部加消力槛的改进措施,经实际运用,得到了满意的消能效果。 |
关键词: 蘑菇湖水库 泄水涵洞 消能 消力池 水工模型试验 |
DOI: |
分类号:TV653.1 |
基金项目: |
|
Improvement of baffle measures downstream of the draw-off culvert of Moguhu Reservoir |
LIU Huan-fang,ZHANG Min,LI Xue-qin,WU Yu-feng
|
Abstract: |
The status quo and existing problems of the energy dissipation measures for the downstream area of the draw-off culvert of Moguhu Reservoir are analyzed. Based on the hydraulic calculation and hydraulic model test of the horizontal diffusion plunge pool with vertical abutment walls, the improvement measure with a baffle sill at the end of the plunge pool is presented, and the energy dissipation is satisfied. |
Key words: draw-off culvert,plunge pool,energy dissipation,Moguhu Reservoir |